health
Calculate Schedule Health Score
Calculate comprehensive schedule health score (0-100) based on deterministic analysis.
This endpoint performs:
- DAG construction and validation
- Critical Path Method (CPM) calculation
- Float analysis and erosion detection
- Critical path density evaluation
- Structural integrity assessment
- Weighted composite scoring per DCMA/GAO/AACE standards
Performance Target: Response time <5s for 1,000 tasks (Phase 1A)
Task Limits:
- Synchronous processing: up to 1,000 tasks
- Tier-based limits: Free (500), Professional (5,000), Enterprise (50,000+)
Compliance:
- DCMA 14-Point Assessment
- GAO Schedule Assessment Guide
- AACE RP 92R-19 (Schedule Health Metrics)
- PMBOK 8 Section 4.5
post/api/v1/health/score
Request
- Base URL: https://api.bellatorsi.com (the document declares no server; this is the origin it was published from)
- URL: https://api.bellatorsi.com/api/v1/health/score
- Auth: none declared
Headers
x-api-keystring nullable
authorizationstring nullable
x-bellator-internal-dispatchstring nullable
Request body
Example request
{
"tasks": [
{
"duration_days": 10,
"id": "T1",
"percent_complete": 0,
"planned_finish": "2025-01-15",
"planned_start": "2025-01-01",
"predecessors": []
},
{
"duration_days": 15,
"id": "T2",
"percent_complete": 0,
"planned_finish": "2025-02-05",
"planned_start": "2025-01-16",
"predecessors": [
"T1"
]
}
]
}Response
Success - Health score calculated
Example response
{
"data": {
"breakdown": {
"criticality_score": 90,
"density_score": 80,
"float_erosion_score": 85,
"structural_score": 95
},
"confidence": 0.95,
"details": {
"cpm": {
"critical_path_length": 12,
"project_duration_days": 45
},
"criticality": {
"critical_density_pct": 45,
"critical_task_count": 45,
"critical_tasks": [
{
"float_days": 0,
"id": "T1",
"name": "Foundation"
}
],
"near_critical_tasks": [
{
"float_days": 2,
"id": "T2",
"name": "Framing"
}
],
"recommendations": [
"HIGH PRIORITY: 45 of 100 tasks (45.0%) are on the critical path",
"[PMBOK 2.7.5.2] Review task dependencies for opportunities to create parallel work streams (fast-tracking)",
"[AACE RP 27R-03] Add time buffers (contingency reserves) before major milestones to protect against schedule delays"
],
"total_tasks": 100
},
"float_erosion": {
"average_float_days": 2.3,
"critical_ratio_pct": 45,
"max_float_days": 8.5,
"min_float_days": 0,
"recommendations": [
"[AACE RP 27R-03] Limited schedule flexibility with average schedule reserve of 2.3 days",
"[PMBOK 2.8.4.3] Implement proactive risk management to protect remaining float"
],
"tasks_with_low_float": [
{
"float_days": 2,
"id": "T2",
"name": "Framing"
}
]
},
"structural": {
"dangling_tasks": [],
"issues": [],
"missing_logic_count": 0,
"recommendations": []
}
},
"grade": "B",
"score": 85.5,
"top_signals": [
"High critical path density (45%)",
"Low average float (2.3 days)"
]
}
}Changes
No recorded changes to this operation across all 1 revision of this API.