project-maintenance-navigation

Export a complete project

Depending on the size of the exported project, the export process may take a while. When the project is being exported, any data load processes scheduled to run during that time will be pending and will be resumed when the export process completes. To avoid this situation, you can export a project without data and then load the data to a new (cloned) project instead.

Request

  • exportUsers (boolean, required) - Specifies whether to include users in the export. Default: 1

  • exportData (boolean, required) - Specifies whether to include project data in the export. Default: 1

  • authorizedUsers (string, optional) - Comma-separated list of email addresses of users authorized to import the project. Surround email addresses with double quotes.

  • excludeSchedules (boolean, optional) - Specifies whether to include scheduled Emails in the export. All schedules you import to a project are enabled, even if they were disabled when exported. To disable a schedule, click Disable on the Schedule Details pane. Default: 0

  • crossDataCenterExport (boolean, optional) - Specifies whether export can be used in any data center. Default: 0

Response

  • status (uri) - URI where you can poll for the status of the export.

  • token (string) - Token to use to import the exported metadata.

post/gdc/md/{project_id}/maintenance/export

Request

  • Base URL
    https://secure.gooddata.com
  • Auth
    none declared

Path parameters

project_idstring required

The ID of the project you want to export.

Request body

Response

_

Changes

No recorded changes to this operation across all 1 revision of this API.