IBC test and inspection due dates
Next leakproofness test, 2.5 and 5-year inspections, last month the IBC may be filled and, for plastic and composite IBCs under UN/ADR, the end of the five-year life. US 49 CFR 180.352 sets no five-year limit. Send insp as well as leak; without it the inspection counts from manufacture.
get/api/ibc-dates
Request
- Base URL: https://fortitude21.com
- URL: https://fortitude21.com/api/ibc-dates
- Auth: none declared
Query parameters
markstring
The IBC UN mark; code and month of manufacture are read from it
codestring
IBC code, e.g. 31HA1, if no mark
madestring
Month of manufacture: MM/YYYY, MM/YY, YYYY-MM or "March 2024"
leakstring
Month of the last leakproofness test
inspstring
Month of the last inspection
repairstring
Month of the last repair
bottlestring
Month the inner receptacle was replaced (remanufactured composite IBCs)
regime'un' | 'us'
un (default) or us
lang'en' | 'ja'
en or ja
Response
The answer
Changes