title: "Resource Analysis"
method: POST
path: "/api/v1/analysis/resources"
tags: ["Analysis"]
---

# Resource Analysis

`POST /api/v1/analysis/resources`

## Request

- Base URL: `https://api.bellatorsi.com` (the document declares no server; this is the origin it was published from)
- URL: `https://api.bellatorsi.com/api/v1/analysis/resources`
- Auth: none declared

Run a time-phased resource analysis on a schedule.

Accepts a schedule payload (tasks), optional resource availability
declarations, and analysis options. Returns demand profiles per resource,
over-allocation periods, leveling candidates, and a composite risk score.

## Headers

- `x-api-key` string, nullable
- `authorization` string, nullable
- `x-bellator-internal-dispatch` string, nullable

## Request body

- ResourceAnalysisRequest: Request for POST /api/v1/forensics/resource-analysis.
  - `tasks` Task[], required: Schedule tasks
    - `id` string, required: Unique task identifier
    - `duration_days` number: Task duration in days
    - `predecessors` union[]: List of predecessor task IDs or dependency links. Supports: 'T1', 'T1FS+5 d', 'T2SS-2 d', or DependencyLink objects
      - union
        - string
        - object
        - DependencyLink: Rich dependency link with relationship type and lag/lead. Supports parsing from various scheduling tool formats including: - MS Project: "10FS+5 d", "/path/file.mpp/10FS+5 d" - Primavera P6: Similar format with XER encoding - Server-based: "<ServerFile>10FS+5 d" - Simple: "10" (defaults to FS with zero lag) Examples: >>> DependencyLink(task_id="10", relationship_type="FS", lag_days=5.0) >>> DependencyLink.from_string("10FS+5 d") >>> DependencyLink.from_string("15SS-2 d")
          - `task_id` string, required: Predecessor task ID
          - `relationship_type` 'FS' | 'SS' | 'FF' | 'SF': Task relationship types per PMBOK 6.3.2.2. Attributes: FINISH_START: Predecessor finish → successor start (most common, ~90%) START_START: Predecessor start → successor start (~5%) FINISH_FINISH: Predecessor finish → successor finish (~4%) START_FINISH: Predecessor start → successor finish (rare, ~1%)
          - `lag_days` number: Lag (positive) or lead (negative) in days
          - `is_external` boolean: True if link to external project file
          - `external_path` string, nullable: Path to external file if is_external=True
    - `name` string, nullable: Task name
    - `resource` string, nullable: Resource assigned to task
    - `resources` string[]: List of resources assigned (for multi-resource tasks)
    - `percent_complete` number: Percent complete (0-100)
    - `physical_percent_complete` number, nullable: Physical percent complete (0-100). Manual EVM entry by scheduler (MSP PhysicalPercentComplete). Authoritative for BCWP calculations. Captured separately from percent_complete on MSP imports.
    - `planned_start` string, date, nullable: Planned start date (ISO 8601)
    - `planned_finish` string, date, nullable: Planned finish date (ISO 8601)
    - `actual_start` string, date, nullable: Actual start date (ISO 8601)
    - `actual_finish` string, date, nullable: Actual finish date (ISO 8601)
    - `baseline_start` string, date, nullable: Baseline start date (ISO 8601)
    - `baseline_finish` string, date, nullable: Baseline finish date (ISO 8601)
    - `constraint_type` string, nullable: Constraint type: ASAP, ALAP, SNET, SNLT, FNET, FNLT, MSO, MFO
    - `constraint_date` string, date, nullable: Constraint date if applicable (ISO 8601)
    - `task_type` string, nullable: Task type classification. Valid values: task (default), milestone, loe, summary, schedule_margin, planning_package, slpp, schedule_visibility. Drives DCMA check exclusions per PAM 200.1 § 3.2.
    - `wbs_code` string, nullable: WBS code (e.g., '1.2.3')
    - `organization_code` string, nullable: Org/dept identifier for anomaly categorization (Progress Audit)
    - `custom_field_map` object, nullable: All WBS/OBS-pattern custom fields discovered in this MS Project file, keyed by alias (e.g., 'CWBS', 'OBS'). Null for XER imports or when no matching aliases exist.
    - `forecast_start` string, date, nullable: Current forecast start date (ISO 8601)
    - `forecast_finish` string, date, nullable: Current forecast finish date (ISO 8601)
    - `total_float_days` number, nullable: Pre-computed total float in days. Auto-computed by CPM if absent.
    - `baseline_duration_days` number, nullable: Baseline duration in days. Auto-computed from baseline dates if absent.
    - `delay_category` string, nullable: Delay attribution category. Valid values: owner, contractor, design, procurement, weather, force_majeure.
    - `earned_value` number, nullable: Earned Value (BCWP) in cost units. Requires options.include_ev_validation.
    - `budgeted_cost` number, nullable: Budgeted Cost of Work Scheduled (BCWS) in cost units.
    - `approval_required` boolean, nullable: Whether this task requires explicit approval before it can start.
    - `approval_status` string, nullable: Approval workflow state. Valid values: not_required, pending, approved, rejected.
  - `status_date` string, nullable: Schedule status date (ISO 8601 YYYY-MM-DD). When omitted, today's date is used as the resource loading window anchor.
  - `resource_availability` AppModelsSchemasResourceAvailability2[], nullable: Optional declared resource capacities
    - `resource_name` string, required: Resource name (must match task resource fields)
    - `units_per_day` number: Available units per day
    - `available_from` string, date, nullable: Availability start date (ISO 8601)
    - `available_to` string, date, nullable: Availability end date (ISO 8601)
  - `options` ResourceAnalysisOptions: Options controlling resource analysis behaviour.
    - `period_size_days` integer: Histogram bucket size in days
    - `include_histogram_data` boolean: Include demand histogram per resource
    - `include_leveling_candidates` boolean: Include leveling candidate tasks
    - `include_critical_path_resources` boolean: Include CP resource section
    - `include_resource_curves` boolean: Include cumulative resource curves
    - `over_allocation_threshold` number: Multiplier of declared capacity (or 1.0/day default) that triggers over-allocation
    - `exclude_task_types` string[]: Task types to exclude from analysis (e.g. 'loe', 'summary')
    - `fields` string[], nullable: Response fields to include (sparse fieldset)

## Response `200`

Successful Response

- BellatorResponseResourceAnalysisData
  - `status` 'pass' | 'fail' | 'warning' | 'info', required: Top-level result status — always present in every response.
  - `score` number, nullable
  - `grade` 'A' | 'B' | 'C' | 'D' | 'F': Letter grade derived from a 0–100 score. Null on non-scoring endpoints.
  - `summary` string, nullable
  - `breakdown` object, nullable
  - `findings` Finding[]
    - `code` string, required: Stable machine-readable identifier e.g. DCMA_CHECK_8_HIGH_DURATION
    - `severity` 'critical' | 'high' | 'medium' | 'low' | 'info', required: Severity level for findings; reused as priority level for recommendations.
    - `title` string, required: Short human-readable label
    - `description` string, required: Full explanation of the issue
    - `standard` string, nullable: Standard citation e.g. 'DCMA PAM 200.1 Check #8'
    - `affected_tasks` string[]: Task IDs implicated by this finding
    - `metric_value` number, nullable: Observed measurement e.g. 60.0 days
    - `threshold` number, nullable: Threshold that was violated e.g. 44.0 days
  - `recommendations` Recommendation[]
    - `priority` 'critical' | 'high' | 'medium' | 'low' | 'info', required: Severity level for findings; reused as priority level for recommendations.
    - `action` string, required: What to do — specific and actionable
    - `standard` string, nullable: Supporting standard citation
    - `finding_codes` string[]: Finding.code values this recommendation addresses
  - `data` ResourceAnalysisData: Data payload for POST /api/v1/forensics/resource-analysis.
    - `summary` ResourceAnalysisSummary, required: High-level summary of resource analysis results.
      - `total_resources` integer, required
      - `over_allocated_resources` integer, required
      - `critical_path_resources` integer, required
      - `resource_coverage_pct` number, required
      - `loe_excluded_count` integer, required
      - `dcma_check_10_compliant` boolean, required
      - `dcma_check_10_details` string, required
      - `peak_demand_period` string, nullable
      - `total_resource_days` number, required
    - `resource_profiles` ResourceProfile[]
      - `resource_name` string, required
      - `total_task_days` number, required
      - `assigned_task_count` integer, required
      - `on_critical_path` boolean, required
      - `declared_capacity_per_day` number, nullable
      - `peak_demand_per_day` number, required
      - `over_allocation_periods` OverAllocationPeriod[]
        - `period_start` string, required
        - `period_end` string, required
        - `demand_units` number, required
        - `capacity_units` number, required
        - `over_allocation_ratio` number, required
        - `severity` 'minor' | 'moderate' | 'critical', required
        - `conflicting_tasks` string[]
      - `histogram` HistogramBucket[]
        - `period_start` string, required
        - `period_end` string, required
        - `demand_units` number, required
        - `capacity_units` number, nullable
        - `utilization_pct` number, nullable
      - `cumulative_curve` CumulativeCurveBucket[]
        - `date` string, required
        - `cumulative_task_days` number, required
    - `critical_path_resources` CriticalPathResources: Resources that appear on the critical path.
      - `resource_names` string[]
      - `critical_path_task_assignments` CPResourceAssignment[]
        - `task_id` string, required
        - `task_name` string, required
        - `resource_name` string, required
        - `early_start` string, required
        - `early_finish` string, required
        - `duration_days` number, required
        - `over_allocated_during_task` boolean
      - `resources_over_allocated_on_cp` string[]
    - `leveling_candidates` LevelingCandidate[]
      - `task_id` string, required
      - `task_name` string, required
      - `resource_name` string, required
      - `total_float_days` number, required
      - `free_float_days` number, required
      - `early_start` string, required
      - `latest_allowable_start` string, required
      - `leveling_window_days` integer, required
      - `resolves_conflict_with` string[]
      - `leveling_priority` 'high' | 'medium' | 'low', required
    - `unresourced_tasks` UnresourcedTask[]
      - `task_id` string, required
      - `task_name` string, required
      - `duration_days` number, required
      - `on_critical_path` boolean, required
    - `resource_risk_score` ResourceRiskScore, required: Composite resource risk score.
      - `score` number, required
      - `grade` 'A' | 'B' | 'C' | 'D' | 'F', required
      - `components` ResourceRiskComponents, required: Component scores that make up the resource risk score.
        - `over_allocation_severity` number, required
        - `coverage_gap` number, required
        - `cp_resource_conflict` number, required
      - `explanation` string, required
    - `processing_metadata` object: Processing metadata (task count, options, etc.)
  - `simulation` SimulationEnvelope: Probabilistic simulation outputs for Tier 3 endpoints. Null on all Tier 1 and Tier 2 responses. When Tier 3 launches, this field transitions from null to populated without changing any other envelope field — existing consumers are unaffected.
    - `method` string, required: Simulation method: monte_carlo | latin_hypercube
    - `trial_count` integer, required
    - `duration_days` PercentileResult: Percentile distribution across simulation trials. Reserved for Tier 3 Monte Carlo / risk simulation endpoints (v0.3.0+).
      - `p10` number, required: 10th percentile outcome
      - `p50` number, required: 50th percentile (median)
      - `p80` number, required: 80th percentile — common contract delivery threshold
      - `p90` number, required: 90th percentile
      - `mean` number, required
      - `std_dev` number, required
    - `cost` PercentileResult: Percentile distribution across simulation trials. Reserved for Tier 3 Monte Carlo / risk simulation endpoints (v0.3.0+).
      - `p10` number, required: 10th percentile outcome
      - `p50` number, required: 50th percentile (median)
      - `p80` number, required: 80th percentile — common contract delivery threshold
      - `p90` number, required: 90th percentile
      - `mean` number, required
      - `std_dev` number, required
    - `completion_date` object, nullable: Map of p-value strings to ISO completion dates e.g. {'p50': '2027-04-15'}
  - `metadata` ResponseMetadata, required: Audit trail and processing context — always present, never null.
    - `task_count` integer, required: Number of tasks in the submitted schedule
    - `processing_time_ms` integer, nullable: Wall-clock processing time in milliseconds
    - `api_version` string: API version that produced this response
    - `endpoint` string, required: Endpoint path e.g. /api/v1/health/score
    - `standards_applied` string[]: Standards consulted during analysis e.g. ['DCMA PAM 200.1', 'GAO BP-2']
    - `confidence` number, nullable: Confidence in the result (0–1). Present on scoring endpoints.
    - `status_date` string, nullable: ISO date used as analysis reference point. Present on time-aware analyses.

## Other responses

- `422`: Validation Error

---

[API](https://skmtc.dev/bellatorsi/apis/bellator-schedule-intelligence-apis.md) · [All operations](https://skmtc.dev/bellatorsi/apis/bellator-schedule-intelligence-apis/llms.txt) · [OpenAPI document](https://skmtc.dev/bellatorsi/apis/bellator-schedule-intelligence-apis/revisions/03e7b786e43b?raw)